ACT - Capital Budget Amendment 2026-75 6 appearances active
CBA-RKD02-Kensico Dam Plaza Storage Building
Sponsors
County Executive
Topics
Summary
This Act amends the 2026 County Capital Budget to increase appropriations for Capital Project RKD02, the Kensico Dam Plaza Storage Building. The previous appropriation was $7,850,000, and this amendment adds $2,500,000, bringing the revised total appropriation to $10,350,000. The method of financing will be through Bonds and/or Notes. The estimated annual cost for principal and interest is $867,183, with a total debt service of $13,007,741 over the bond term. This project is projected to fund 113 FTE jobs.
Committee Timeline
Board of Legislators
February 9, 2026
Parks & Environment
February 24, 2026
Board of Legislators
March 2, 2026
Want to know when this matter moves?
Set Up Alerts