Change Order No. 24 to Contract 9358, Bartillon Shelter, to Miron Construction Co., Inc., for $107,243.44 and a time extension to 2/18/26. (District 12).
Topics
Summary
Summary
This is Change Order No. 24 to Contract 9358 for the Bartillon Shelter project, awarded to Miron Construction Co., Inc. The change order adds $107,243.44 to the contract, bringing the total contract sum to $22,565,543.88. This represents a 0.50% increase of the original contract value. Additionally, the project completion date is extended to February 18, 2026. The reasons cited for the change order include design changes such as shower bench removal and replacement, underground utility conflicts, and expanded scope due to actual versus estimated quantities.
Citizen Impact
Residents should be aware of a cost increase and project delay for the Bartillon Shelter. The project completion is now extended to February 18, 2026, with an additional $107,243.44 in costs.
Confidence
high
Committee Timeline
Want to know when this matter moves?
Set Up Alerts