Award of Contract Consent M&C 26-0175 1 appearance active
(CD 2) Authorize Execution of Change Order No. 2, in the Amount of $640,368.77 and the Addition of 80 Calendar Days to the Construction Contract with The Fain Group, LLC, fka The Fain Group, Inc., for Additional Scope Including Planting Trees, Irrigation, and Paving Items for the Long Avenue ARPA Pedestrian Safety Improvements Project for a Revised Contract Amount of $4,522,556.97 (2022 Bond Program)